Thursday, June 2, 2022

CONSTRUCTION OF MINDANAO'S LONGEST BRIDGE NOW HALFWAY DONE

Department of Public Works and Highways (DPWH) Acting Secretary Roger G. Mercado is keen to make the most of his remaining few days as member of the Cabinet of President Rodrigo Roa Duterte administration. 
Secretary Mercado declared that although time is running out for the term of President Duterte will end this June 30, his duty to the public is far from over and will not take a pause in fulfilling the enormous job at DPWH of providing the Filipino people with quality infrastructure. 
The DPWH Chief together with Undersecretary and Build Build Build Chief Implementer Emil K. Sadain inspected on Wednesday, June 1, 2022 the on-going Panguil Bay Bridge Project, listed among the 119 infrastructure flagship projects under the “Build, Build, Build” Program. 
The two (2) officials were joined in the project visit by Undersecretary for Mindanao Operations Eugenio R. Pipo Jr.; Lanao Del Norte Governor Imelda Quibranza-Dimaporo and Congresman Abdullah D. Dimaporo; Assistant Secretaries Ador G. Canlas, Antonio V. Molano Jr., Wilfredo S. Mallari, Mel John I. Verzosa and Rolito D. Manalo; and Project Director Sharif Madsmo H. Hasim and Project Manager Teresita V. Bauzon of DPWH Unified Project Management Office (UPMO) Roads Management Cluster 2 (Multilateral). 
When finished, the 3.17 kilometer two-way two-lane Panguil Bay Bridge, which will link Tangub City in Misamis Occidental with the Municipality of Tubod in Lanao del Norte, will be Mindanao’s longest bridge.

With funding assistance from South Korea, the ₱7.37 Billion project is being implemented by the DPWH UPMO Operations. 
Undersecretary Sadain, in-charge of DPWH UPMO Operations, reported in his briefing that the project has achieved 51.4 percent completion to date, recovering from the delays in the delivery of equipment and materials in 2020 brought about by the unprecedented impacts of the global coronavirus pandemic. 

“I am delighted that the work is now progressing at a faster pace using state-of-the-art engineering equipment and adopting modern technology in bridge construction”, added Secretary Mercado.  

The bridge project that has gained the full support of the Provincial Government of Lanao Del Norte and Misamis Occidental has an established Multi-Partite Monitoring Team to properly monitor and successfully implement the Panguil Bay Bridge Project. 
Targetted for completion by December 2023, the Panguil Bay Bridge Project will make commuting easier as it will only take 7 minutes from Tangub to Tubod compared to 1 hour and 30 minutes via Roll-On Roll-Off vessels operating from Ozamis to Mucas or land travel through Panguil Bay road of 2 to 2 and a half hours over a total length of 100 kilometers. 

Source and Photos: 
Department of Public Works and Highways

Monday, June 15, 2020

NLEX Harbor Link Project - Metro Manila

 




NLEX Harbor Link Project (Segments 8.1, 8.2, 9 & 10)

Project Description: 
The project involves the 21.60-km extension of the NLEX eastward from Valenzuela City to Mel Lopez Boulevard/R10, (NLEX Harbor Link Project comprising of Segments 9, 10 and Exit Ramp to R10) and westward from Valenzuela City to Commonwealth Avenue in Quezon City, (Circumferential Road 5, C-5, comprising of Segments 8.1 and 8.2). 

ONGOING SEGMENT:
A) SEGMENT 8.2 – is a proposed 8.30 kms 4-lane divided (2x2) expressway from Segment 8.1 at Mindanao Avenue, traversing westward to Republic Avenue and turning right to Luzon Avenue up to Commonwealth Avenue in Quezon City.
      Section 1A: Mindanao Avenue to Quirino Highway, 2.0 kms.
     Section 1B: Quirino Highway to Regalado Avenue, 3.80 kms.
     Section 1C: Regalado Avenue to Congressional Avenue, 2.50 kms

COMPLETED SEGMENTS:
B) SEGMENT 10, EXIT RAMP to R-10 - is a 2.60 km. 4-lane (initial) elevated ramp extending the NLEX Harbor Link Segment 10 exit to Radial Road 10 (R-10), using C-3 Road as its route.

C) SEGMENT 10 - is a 5.58-km. 6-lane divided (2x3) elevated expressway connecting McArthur Highway and C-3. It will utilize the existing PNR railroad tracks that cut across Valenzuela City and Malabon City.

D) SEGMENT 9 - is a 2.42-km. 4-lane (2x2) that connects NLEX Mindanao Avenue Link (Segment 8.1) at the SMART Connect Interchange to McArthur Highway in Valenzuela City.
E) SEGMENT 8.1 - a 2.7-km expressway connecting the NLEX, at its Valenzuela City junction, to Mindanao Avenue in Quezon City. A major component is the Cloverleaf SMART Connect Interchange crossing the main expressway. It provided motorists with alternative entry and exit ramps to the NLEX.

Read more of this project here DPWH - NLEX_harbor_link project 



Quezon City (QC) to Port Area in Manila is now travelled in just 20 minutes (commute)  read here NLEX Corp by Metro Pacific 



Photo courtesy: NLEX Corp